Sanitary Drainage & Indirect/Special Waste
Content area 5 of the Vermont master plumber exam.
Sanitary Drainage Systems
Reference text for the sanitary drainage area. Every rule below is written from the printed line of
the 2024 International Plumbing Code (IPC 2024) that carries it, and each rule names the section it
comes from. Where the printed line does not state a value, no value is stated here.
1. General
The chapter governs the materials, design, construction and installation of sanitary drainage systems
(IPC 2024, 701.1). Sanitary drainage piping from plumbing fixtures in buildings, and sanitary drainage
piping systems from premises, must be connected to a public sewer; where a public sewer is not
available they must be connected to a private sewage disposal system in compliance with state or local
requirements, and, where such requirements do not exist, to an approved private sewage disposal system
in accordance with the International Private Sewage Disposal Code (IPC 2024, 701.2). The exception
covers piping and systems that convey only the discharge from bathtubs, showers, lavatories, clothes
washers and laundry trays, provided they are connected to a system in accordance with Chapter 13 or 14
(IPC 2024, 701.2, Exception).
A building having plumbing fixtures installed and intended for human habitation, occupancy or use on
premises abutting on a street, alley or easement in which there is a public sewer must have a separate
connection with the sewer; where located on the same lot, multiple buildings may connect to a common
building sewer that connects to the public sewer (IPC 2024, 701.3). Sewage or other waste deleterious
to surface or subsurface waters must not be discharged into the ground or into any waterway unless
first rendered innocuous through an approved form of treatment (IPC 2024, 701.4), and waste
detrimental to the public sewer system or to the functioning of the sewage-treatment plant must be
treated and disposed of in accordance with Section 1003 as directed by the code official (IPC 2024,
701.5). The sanitary drainage system is tested in accordance with Section 312 (IPC 2024, 701.6), and
engineered sanitary drainage systems must conform to Sections 316 and 713 (IPC 2024, 701.7).
2. Materials and joints
Sections 702.1 (above-ground sanitary drainage and vent pipe), 702.2 (underground building sanitary
drainage and vent pipe), 702.3 (building sewer pipe) and 702.4 (fittings) publish the materials and
the standards for those applications. Where the wastewater temperature will be greater than 140°F
(60°C), the sanitary drainage piping material must be rated for the highest temperature of the
wastewater (IPC 2024, 702.5). Section 702.6 governs chemical waste systems and Section 702.7 lead
bends and traps.
Section 705 contains the provisions applicable to joints specific to sanitary drainage piping
(IPC 2024, 705.1): 705.2 ABS plastic, 705.3 cast iron, 705.4 concrete joints, 705.5 copper pipe,
705.6 copper tubing, 705.7 borosilicate glass joints, 705.8 steel, 705.9 lead, 705.10 PVC plastic,
705.11 vitrified clay, 705.12 polyethylene plastic pipe, 705.13 polyolefin plastic, 705.14
polyvinylidene fluoride plastic, 705.15 polypropylene plastic, 705.16 joints between different
materials, 705.17 drainage slip joints, 705.18 caulking ferrules, 705.19 soldering bushings and
705.20 stainless steel drainage systems. Prohibited joints and connections in
drainage piping are: cement or concrete joints; mastic or hot-pour bituminous joints; joints made
with fittings not approved for the specific installation; joints between different diameter pipes made
with elastomeric rolling O-rings; solvent-cement joints between different types of plastic pipe except
where provided for in Section 705.16.4; and saddle-type fittings (IPC 2024, 707.1).
3. Building sewer
The proximity of a sewer to a water service must comply with Section 603.2 (IPC 2024, 703.1). Where a
building sewer or building drain is installed on filled or unstable ground, the drainage pipe must
conform to one of the standards for ABS plastic pipe, cast-iron pipe, copper or copper-alloy tubing,
PVC plastic pipe or polypropylene plastic pipe indicated in Table 702.3 (IPC 2024, 703.2). Where
separate systems of sanitary drainage and storm drainage are installed in the same property, the
sanitary and storm building sewers or drains may be laid side by side in one trench (IPC 2024, 703.3).
Where the entire sanitary drainage system of an existing building is replaced, existing building
drains under concrete slabs and existing building sewers that will serve the new system must be
internally examined to verify that the piping is sloping in the correct direction, is not broken, is
not obstructed and is sized for the drainage load of the new plumbing drainage system to be installed
(IPC 2024, 703.4). Cleanouts on building sewers are located as indicated in Section 708 (IPC 2024,
703.5), and where the public sewer is a combined system for both sanitary and storm water the sanitary
sewer must be connected independently to the public sewer (IPC 2024, 703.6).
4. Drainage piping installation
4.1 Slope
Horizontal drainage piping must be installed in uniform alignment at uniform slopes. The slope must be
not less than Table 704.1 shows, except that where the drainage piping is upstream of a grease
interceptor the slope must be not less than 1/4 inch per foot (2 percent slope) (IPC 2024, 704.1).
| Size (inches) | Minimum slope (inch per foot) |
|---|---|
| 2 1/2 or less | 1/4 |
| 3 to 6 | 1/8 |
| 8 or larger | 1/16 |
For SI: 1 inch = 25.4 mm, 1 inch per foot = 83.33 mm/m. Slopes for piping draining to a grease
interceptor comply with Section 704.1 (IPC 2024, Table 704.1, footnote a).
4.2 Size reduction, offsets and future fixtures
The size of the drainage piping must not be reduced in the direction of flow. The following are not
considered a reduction in size in the direction of flow: a 4-inch by 3-inch (102 mm by 76 mm) water
closet flange; a water closet bend fitting having a 4-inch (102 mm) inlet and a 3-inch (76 mm) outlet,
provided the 4-inch leg of the fitting is upright and below, but not necessarily directly connected
to, the water closet flange; and an offset closet flange (IPC 2024, 704.2).
Horizontal branches must connect to the bases of stacks at a point located not less than 10 times the
diameter of the drainage stack downstream from the stack, and must connect to horizontal stack offsets
at a point located not less than 10 times the diameter of the drainage stack downstream from the
upper stack (IPC 2024, 704.3). Drainage piping for future fixtures must terminate with an approved cap
or plug (IPC 2024, 704.4).
5. Connections and fittings
Connections and changes in direction of the sanitary drainage system must be made with approved
drainage fittings; connections between drainage piping and fixtures conform to Section 405 (IPC 2024,
706.1). Fittings must not have ledges, shoulders or reductions capable of retarding or obstructing
flow in the piping, and threaded drainage pipe fittings must be of the recessed drainage type; the
section does not apply to tubular waste fittings used to convey vertical flow upstream of the trap
seal liquid level of a fixture trap (IPC 2024, 706.2).
Fittings must be installed to guide sewage and waste in the direction of flow, and changes in
direction must be made by fittings installed in accordance with Table 706.3. Change in direction by
combination fittings, side inlets or increasers must be installed in accordance with Table 706.3 based
on the pattern of flow created by the fitting. Double sanitary tee patterns must not receive the
discharge of back-to-back water closets and fixtures or appliances with pumping action discharge;
back-to-back water closet connections to double sanitary tees are permitted where the horizontal
developed length between the outlet of the water closet and the connection to the double sanitary tee
pattern is 18 inches (457 mm) or greater (IPC 2024, 706.3 and Exception).
Table 706.3 — fittings for change in direction ("X" = permitted):
| Type of fitting pattern | Horizontal to vertical | Vertical to horizontal | Horizontal to horizontal |
|---|---|---|---|
| Sixteenth bend | X | X | X |
| Eighth bend | X | X | X |
| Sixth bend | X | X | X |
| Quarter bend | X | Xᵃ | Xᵃ |
| Short sweep | X | Xᵃ,ᵇ | Xᵃ |
| Long sweep | X | X | X |
| Sanitary tee | Xᶜ | — | — |
| Wye | X | X | X |
| Combination wye and eighth bend | X | X | X |
Fitting limitations, as the printed table carries them on the marked cells (IPC 2024,
Table 706.3, footnotes a, b and c): the fittings marked a are only permitted for a 2-inch or smaller
fixture drain; the cell marked b carries "three inches or larger"; and the double sanitary tee
limitation is Section 706.3.
Heel-inlet quarter bends are an acceptable means of connection except where the quarter bend serves a
water closet; a low-heel inlet must not be used as a wet-vented connection; side-inlet quarter bends
are an acceptable means of connection for drainage, wet venting and stack venting arrangements
(IPC 2024, 706.4).
6. Cleanouts
Cleanouts must be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.12
(IPC 2024, 708.1). The principal requirements:
100 feet (30 480 mm), and building drains must have cleanouts at intervals of not more than 100 feet
(30 480 mm) except where manholes are used instead of cleanouts, in which case the manholes must be
located at intervals of not more than 400 feet (122 m); the interval is measured from the cleanout
or manhole opening, along the developed length of the piping, to the next drainage fitting providing
access for cleaning, the end of the horizontal drain or the end of the building drain (IPC 2024,
708.1.1).
100 feet (30 480 mm); building sewers 8 inches (203 mm) and larger must have a manhole located not
more than 200 feet (60 960 mm) from the junction of the building drain and building sewer and at
intervals of not more than 400 feet (122 m) (IPC 2024, 708.1.2).
the junction or within 10 feet (3048 mm) of the developed length of piping upstream of the
junction; removal of the water closet must not be required to provide cleanout access (IPC 2024,
708.1.3).
direction greater than 45 degrees, a cleanout must be installed at the change of direction; where
more than one such change occurs within 40 feet (12 192 mm) of developed length, the cleanout
installed for the first change serves all changes in direction within that 40 feet (IPC 2024,
708.1.4).
4 inches (102 mm) need not be larger than 4 inches (102 mm); a removable P-trap with slip or ground
joint connections can serve as a cleanout for drain piping one size larger than the P-trap size;
cleanouts located on stacks can be one size smaller than the stack size; and the size of cleanouts
for cast-iron piping can be in accordance with the referenced standards for cast-iron fittings in
Table 702.4 (IPC 2024, 708.1.5 and Exceptions).
acceptable as a cleanout equivalent (IPC 2024, 708.1.6). Cleanout plugs must be of copper-alloy,
plastic or other approved materials (borosilicate glass for borosilicate glass piping systems),
copper-alloy plugs conforming to ASTM A74 and limited to metallic piping systems, plastic plugs
conforming to the referenced standards for plastic pipe fittings in Table 702.4, with a raised
square head, a countersunk square head or a countersunk slot head, and manufactured with a blind
end threaded hole where a trim cover screw will be installed (IPC 2024, 708.1.7).
must have gas-tight covers that require tools for removal (IPC 2024, 708.1.8). The installation
arrangement of a cleanout must enable cleaning of drainage piping only in the direction of drainage
flow, except for test tees serving as cleanouts and a two-way cleanout installation approved for
meeting Section 708.1.3 (IPC 2024, 708.1.9).
less than 18 inches (457 mm) from, and perpendicular to, the face of the opening to any
obstruction; cleanouts for 8-inch (203 mm) and larger piping must have a clearance of not less than
36 inches (914 mm) (IPC 2024, 708.1.10).
inside of plenums, within walls, within floor/ceiling assemblies, below grade and in crawl spaces
where the height from the crawl space floor to the nearest obstruction along the path from the
crawl space opening to the cleanout is less than 24 inches (610 mm). Cleanouts with openings at a
finished wall must have the face of the opening within 1 1/2 inches (38 mm) of the finished wall
surface; cleanouts located below grade must be extended to grade level so that the top of the
cleanout plug is at or above grade; and a cleanout installed in a floor or walkway without a trim
cover must have a countersunk plug installed so the top surface of the plug is flush with the
finished surface of the floor or walkway (IPC 2024, 708.1.11).
trim cover fasteners that thread into cleanout plugs must be corrosion resistant, and cleanout plugs
must not be covered with mortar, plaster or any other permanent material (IPC 2024, 708.1.11.1).
Cleanout assemblies in accordance with ASME A112.36.2M must be installed where it is necessary to
protect a cleanout plug from the loads of vehicular traffic (IPC 2024, 708.1.11.2).
where another cleanout of equal size is installed with the required access and clearance (IPC 2024,
708.1.12).
7. Fixture units
Drainage fixture unit values in Table 709.1 designate the relative load weight of different kinds of
fixtures, to be used in estimating the total load carried by a soil or waste pipe and in connection
with Tables 710.1(1) and 710.1(2) (IPC 2024, 709.1).
| Fixture type | Drainage fixture unit value | Minimum size of trap (inches) |
|---|---|---|
| Automatic clothes washers, commercial | 3 | 2 |
| Automatic clothes washers, residential | 2 | 2 |
| Bathroom group as defined in Section 202 (1.6 gpf water closet) | 5 | — |
| Bathroom group as defined in Section 202 (water closet flushing greater than 1.6 gpf) | 6 | — |
| Bathtub (with or without overhead shower or whirlpool attachments) | 2 | 1 1/2 |
| Bidet | 1 | 1 1/4 |
| Combination sink and tray | 2 | 1 1/2 |
| Dental lavatory | 1 | 1 1/4 |
| Dental unit or cuspidor | 1 | 1 1/4 |
| Dishwashing machine, domestic | 2 | 1 1/2 |
| Drinking fountain | 1/2 | 1 1/4 |
| Emergency floor drain | 0 | 2 |
| Floor drains | 2 | 2 |
| Floor sinks | Note h | 2 |
| Kitchen sink, domestic | 2 | 1 1/2 |
| Kitchen sink, domestic with food waste disposer, dishwasher or both | 2 | 1 1/2 |
| Laundry tray (1 or 2 compartments) | 2 | 1 1/2 |
| Lavatory | 1 | 1 1/4 |
| Service sink | 2 | 1 1/2 |
| Sink | 2 | 1 1/2 |
| Urinal | 4 | Note d |
| Urinal, 1 gallon per flush or less | 2 | Note d |
| Urinal, nonwater supplied | 1/2 | Note d |
| Wash sink (circular or multiple), each set of faucets | 2 | 1 1/2 |
| Water closet, flushometer tank, public or private | 4 | Note d |
| Water closet, private (1.6 gpf) | 3 | Note d |
| Water closet, private (flushing greater than 1.6 gpf) | 4 | Note d |
| Water closet, public (1.6 gpf) | 4 | Note d |
| Water closet, public (flushing greater than 1.6 gpf) | 6 | Note d |
Table notes that carry rules: a showerhead over a bathtub or whirlpool bathtub attachment does not
increase the drainage fixture unit value (footnote b); trap size must be consistent with the fixture
outlet size (footnote d); and for traps larger than 3 inches, Table 709.2 is used (footnote a).
Showers are rated on the total flow rate through showerheads and body sprays: 5.7 gpm or less = 2 dfu
with a 1 1/2-inch trap; greater than 5.7 gpm to 12.3 gpm = 3 dfu with a 2-inch trap; greater than
12.3 gpm to 25.8 gpm = 5 dfu with a 3-inch trap; greater than 25.8 gpm to 55.6 gpm = 6 dfu with a
4-inch trap (IPC 2024, Table 709.1).
Where discharges to a waste receptor or to a drainage system are known only in gallons per minute, the
drainage fixture unit values for those flows are computed on the basis that 1 gpm (0.06 L/s) of flow
is equivalent to two drainage fixture units (IPC 2024, 709.3). The drainage fixture unit load of an
indirect waste receptor receiving the discharge of indirectly connected fixtures is the sum of the
drainage fixture unit values of the fixtures that discharge to the receptor, but not less than the
value given for the indirect waste receptor in Table 709.1 or 709.2 (IPC 2024, 709.4). Waste receptors
such as floor drains, floor sinks and hub drains that receive only clear-water waste from display
cases, refrigerated display cases, ice bins, coolers and freezers have a drainage fixture unit value
of one-half (IPC 2024, 709.4.1).
8. Drainage system sizing
The maximum number of drainage fixture units connected to a given size of building sewer, building
drain or horizontal branch of the building drain is determined using Table 710.1(1), and the maximum
number connected to a given size of horizontal branch or vertical soil or waste stack is determined
using Table 710.1(2) (IPC 2024, 710.1).
Table 710.1(1) — building drains and sewers:
| Diameter of pipe (inches) | 1/16 inch slope | 1/8 inch slope | 1/4 inch slope | 1/2 inch slope |
|---|---|---|---|---|
| 1 1/4 | — | — | 1 | 1 |
| 1 1/2 | — | — | 3 | 3 |
| 2 | — | — | 21 | 26 |
| 2 1/2 | — | — | 24 | 31 |
| 3 | — | 36 | 42 | 50 |
| 4 | — | 180 | 216 | 250 |
| 5 | — | 390 | 480 | 575 |
| 6 | — | 700 | 840 | 1,000 |
| 8 | 1,400 | 1,600 | 1,920 | 2,300 |
| 10 | 2,500 | 2,900 | 3,500 | 4,200 |
| 12 | 3,900 | 4,600 | 5,600 | 6,700 |
| 15 | 7,000 | 8,300 | 10,000 | 12,000 |
The minimum size of any building drain serving a water closet is 3 inches (IPC 2024,
Table 710.1(1), footnote a).
9. Offsets in drainage piping in buildings of five stories or more
If a horizontal branch connects to the stack within 2 feet (610 mm) above or below a vertical stack
offset, and the offset is located more than four branch intervals below the top of the stack, the
offset must be vented in accordance with Section 907; those vents are not required where the stack and
its offset are sized as a building drain (IPC 2024, 711.1 and 711.1.1).
A stack with a horizontal offset located more than four branch intervals below the top of the stack
must be vented in accordance with Section 907 and sized as follows: the portion of the stack above
the offset is sized as for a vertical stack based on the total number of drainage fixture units above
the offset; the offset is sized in accordance with Section 710.1.1; and the portion of the stack below
the offset is sized as for the offset or based on the total number of drainage fixture units on the
entire stack, whichever is larger (IPC 2024, 711.2). Those vents are not required where the stack and
its offset are one pipe size larger than required for a building drain and the entire stack and offset
are not less in cross-sectional area than that required for a straight stack plus the area of an
offset vent as provided in Section 907 (IPC 2024, 711.2.1).
Where a vertical offset occurs in a soil or waste stack below the lowest horizontal branch, a change
in diameter of the stack because of the offset is not required; if a horizontal offset occurs below
the lowest horizontal branch, the required diameter of the offset and of the stack below it must be
determined as for a building drain in accordance with Table 710.1(1) (IPC 2024, 711.3).
10. Sumps and ejectors
Building subdrains that cannot be discharged to the sewer by gravity flow must be discharged into a
tightly covered and vented sump from which the liquid is lifted and discharged into the building
gravity drainage system by automatic pumping equipment or other approved method; in other than
existing structures, the sump must not receive drainage from any piping within the building capable of
being discharged by gravity to the building sewer (IPC 2024, 712.1). A check valve and a full-open
valve located on the discharge side of the check valve must be installed in the pump or ejector
discharge piping between the pump or ejector and the gravity drainage system, with access to such
valves; they must be located above the sump cover required by Section 712.1 or, where the discharge
pipe from the ejector is below grade, accessibly outside the sump below grade in an access pit with a
removable access cover (IPC 2024, 712.2).
The sump pit must be not less than 18 inches (457 mm) in diameter and not less than 24 inches (610 mm)
in depth unless otherwise approved, provided with access, located so that all drainage flows into the
pit by gravity, constructed of tile, concrete, steel, plastic or other approved materials, with a
solid bottom providing permanent support for the pump, and fitted with a gastight removable cover
installed not more than 2 inches (51 mm) below grade or floor level, adequate to support anticipated
loads; the sump pit is vented in accordance with Chapter 9 (IPC 2024, 712.3.2). The effluent level
control must be adjusted and maintained to at all times prevent the effluent in the sump from rising
to within 2 inches (51 mm) of the invert of the gravity drain inlet into the sump (IPC 2024, 712.3.4).
Discharge pipe and fittings must be constructed of copper or copper-alloy, CPVC, ductile iron, PE or
PVC, rated for the maximum system operating pressure and temperature, compatible with the pipe
material, and suitable for burial where buried in the earth (IPC 2024, 712.3.3.1 and 712.3.3.2).
Pumps connected to the drainage system must connect to a building sewer, building drain, soil stack,
waste stack or horizontal branch drain; where the discharge line connects into horizontal drainage
piping, the connection must be made through a wye fitting into the top of the drainage piping, and
that wye fitting must be located not less than 10 pipe diameters from the base of any soil stack,
waste stack or fixture drain (IPC 2024, 712.3.5).
A sewage pump or sewage ejector must automatically discharge the contents of the sump to the building
drainage system (IPC 2024, 712.4). Macerating toilet systems must comply with ASME A112.3.4/CSA B45.9
and be installed in accordance with the manufacturer's instructions (IPC 2024, 712.4.1). A sewage pump
or ejector must have the capacity and head for the application requirements: pumps or ejectors that
receive the discharge of water closets must be capable of handling spherical solids with a diameter of
up to and including 2 inches (51 mm), and other pumps or ejectors must be capable of handling
spherical solids up to and including 1/2 inch (13 mm). Capacity based on the diameter of the discharge
pipe must be not less than Table 712.4.2 shows; grinder pumps or grinder ejectors that receive the
discharge of water closets must have a discharge opening of not less than 1 1/4 inches (32 mm), and
macerating toilet assemblies that serve single water closets must have a discharge opening of not less
than 3/4 inch (19.1 mm) (IPC 2024, 712.4.2 and Exceptions).
| Diameter of the discharge pipe (inches) | Capacity of pump or ejector (gpm) |
|---|---|
| 2 | 21 |
| 2 1/2 | 30 |
| 3 | 46 |
11. Computerized drainage design, backwater valves and rehabilitation
The sizing, design and layout of the drainage system may be designed by approved computer design
methods; the load is computed from the simultaneous or sequential discharge conditions from fixtures,
appurtenances and appliances or the peak usage design condition; discharge profiles for flow rates
versus time follow the manufacturer's specifications; pipe must be sized to prevent full-bore flow;
pipe size calculations use the pipe wall roughness factor (ks) per the manufacturer's specifications
as modified for aging roughness factors with deposits and corrosion; and horizontal drainage piping
must be designed and installed at slopes in accordance with Table 704.1 (IPC 2024, 713.1, 713.2,
713.2.1, 713.3, 713.3.1 and 713.3.2).
Where plumbing fixtures are installed on a floor with a finished floor elevation below the elevation
of the manhole cover of the next upstream manhole in the public sewer, such fixtures must be protected
by a backwater valve installed in the building drain or horizontal branch serving such fixtures;
fixtures installed on a floor with a finished floor elevation above the elevation of that manhole
cover must not discharge through a backwater valve, except that in existing buildings fixtures above
that elevation are not prohibited from discharging through a backwater valve (IPC 2024, 714.1 and
Exception). Backwater valves must comply with ASME A112.14.1, CSA B181.1 or CSA B181.2 (IPC 2024,
714.2), and must be installed so that access is provided to the working parts (IPC 2024, 714.3).
Sections 715 through 718 govern vacuum drainage systems, replacement of underground building sewers
and building drains by pipe-bursting methods, relining of building sewers and building drains, and
rehabilitation of building sewers and building drains; vacuum drainage systems must be designed per
the manufacturer's instructions and the plans, specifications and other data submitted to the code
official for review and approval prior to installation (IPC 2024, 715.1, 715.2, 716.1, 717.1 and
718.1).
12. Testing the sanitary drainage system
Section 312 governs the tests (IPC 2024, 701.6):
openings in the piping tightly closed except the highest opening, the system filled with water to
the point of overflow; if tested in sections, each opening tightly plugged except the highest
openings of the section under test and each section filled with water, but no section tested with
less than a 10-foot (3048 mm) head of water; in testing successive sections, not less than the upper
10 feet of the next preceding section must be tested, so that no joint or pipe in the building,
except the uppermost 10 feet of the system, is submitted to a test of less than a 10-foot head of
water. The pressure must be held for not less than 15 minutes, and the system must then be tight at
all points (IPC 2024, 312.2).
forcing air into the system until there is a uniform gauge pressure of 5 psi (34.5 kPa) or enough
to balance a 10-inch (254 mm) column of mercury, held for not less than 15 minutes, with adjustments
for ambient temperature or gasket seating made before the test period begins (IPC 2024, 312.3).
uniform gauge pressure of negative 5 pounds per square inch or a negative 10 inches of mercury
column, held without removal of additional air for 15 minutes (IPC 2024, 312.4).
and in sufficient detail to determine compliance; where a smoke test is used it is made by filling
all traps with water and introducing into the entire system a pungent, thick smoke produced by one
or more smoke machines; when the smoke appears at stack openings on the roof, the stack openings
must be closed and a pressure equivalent to a 1-inch water column (248.8 Pa) held for a test period
of not less than 15 minutes (IPC 2024, 312.5).
Indirect and Special Waste
Reference text for the indirect and special waste area. Every rule below is written from the printed
line of the 2024 International Plumbing Code (IPC 2024) that carries it, and each rule names the
section it comes from. Where the printed line does not state a value, no value is stated here.
1. Why indirect waste exists
There are drainage applications in buildings where a backup of liquid waste in a drainage system could
contaminate equipment and appliances. Chapter 8 covers the applications that require an indirect
discharge connection to the building's drainage system, and it carries the provisions for the types of
indirect connections and waste receptor configurations (IPC 2024, Chapter 8, About this chapter).
The chapter governs indirect waste piping and special wastes, and further controls food-handling
establishments, sterilizers, humidifiers, clear-water waste, swimming pools, methods of providing air
breaks or air gaps, and neutralizing devices for corrosive wastes (IPC 2024, 801.1). Devices,
appurtenances, appliances and apparatus intended to serve some special function — such as
sterilization, humidification, distillation, processing, cooling, or storage of ice or foods — and
that discharge to the drainage system, must be provided with protection against backflow, flooding,
fouling, contamination and stoppage of the drain (IPC 2024, 801.2).
2. Where an indirect waste connection is required
Food-handling equipment (in other than dwelling units), clear-water waste, humidifiers, dishwashing
machines and utensils, pots, pans and dishwashing sinks must discharge through an indirect waste pipe
as specified in Sections 802.1.1 through 802.1.7. Fixtures not required to be indirectly connected by
that section, and the exception to Section 301.6, must be directly connected to the plumbing system in
accordance with Chapter 7 (IPC 2024, 802.1). (Section 301.6 prohibits plumbing systems in an elevator
shaft or elevator equipment room, with an exception permitting floor drains, sumps and sump pumps at
the base of the shaft where they are indirectly connected to the plumbing system and comply with
Section 1003.4 — IPC 2024, 301.6 and Exception.)
The specific applications:
discharge through an indirect waste pipe by means of an air gap, and each well of a
multiple-compartment sink must discharge independently to a waste receptor (IPC 2024, 802.1.1).
food service and food establishments must be indirectly connected to the sanitary drainage system by
means of an air gap. Where a floor drain is located within an area subject to freezing, the waste
line serving the floor drain must not be trapped and must indirectly discharge into a waste receptor
located outside of the area subject to freezing. Exception: where protected against backflow by a
backwater valve, such floor drains must be indirectly connected to the sanitary drainage system by
means of an air break or an air gap (IPC 2024, 802.1.2).
discharge potable water to the building drainage system, the discharge must be through an indirect
waste pipe by means of an air gap (IPC 2024, 802.1.3).
deck drains discharge to the building drainage system, the discharge must be through an indirect
waste pipe by means of an air gap (IPC 2024, 802.1.4).
boilers discharge nonpotable water to the building drainage system, the discharge must be through an
indirect waste pipe by means of an air break or an air gap (IPC 2024, 802.1.5).
an air gap or air break into a waste receptor in accordance with Section 802.3 (IPC 2024, 802.1.6).
washing, rinsing or sanitizing of utensils, dishes, pots, pans or service ware used in the
preparation, serving or eating of food, must discharge indirectly through an air gap or an air break
to the drainage system (IPC 2024, 802.1.7).
3. Air gap against air break
The distinction the chapter draws is which method is required, not which is convenient:
| Application | Method required |
|---|---|
| Food handling equipment and fixtures | Air gap (IPC 2024, 802.1.1) |
| Floor drains in walk-in refrigerators or freezers | Air gap; air break or air gap where protected by a backwater valve (IPC 2024, 802.1.2) |
| Potable clear-water waste (sterilizers, relief valves) | Air gap (IPC 2024, 802.1.3) |
| Swimming pools, filter backwash, pool deck drains | Air gap (IPC 2024, 802.1.4) |
| Nonpotable clear-water waste (process tanks, filters, drips, boilers) | Air break or air gap (IPC 2024, 802.1.5) |
| Commercial dishwashing machines | Air gap or air break (IPC 2024, 802.1.6) |
| Sinks for washing, rinsing or sanitizing utensils (other than dwelling units) | Air gap or air break (IPC 2024, 802.1.7) |
The two connections are defined by measurement: the air gap between the indirect waste pipe and the
flood level rim of the waste receptor must be not less than twice the effective opening of the
indirect waste pipe (IPC 2024, 802.3.1), while an air break must be provided between the indirect
waste pipe and the trap seal of the waste receptor (IPC 2024, 802.3.2).
4. Materials and installation of indirect waste piping
Materials, joints, connections and methods used for the construction and installation of indirect
waste piping systems must comply with the applicable provisions of Chapter 7 (IPC 2024, 802.2).
Indirect waste piping must discharge through an air gap or air break into a waste receptor; waste
receptors must be trapped and vented and must connect to the building drainage system (IPC 2024,
802.3). Indirect waste piping that exceeds 30 inches (762 mm) in developed length measured
horizontally, or 54 inches (1372 mm) in total developed length, must be trapped. The exception: where
a waste receptor receives only clear-water waste and does not directly connect to a sanitary drainage
system, the receptor does not require a trap (IPC 2024, 802.3 and Exception).
5. Waste receptors
For other than hub drains that receive only clear-water waste and standpipes, a removable strainer or
basket must cover the outlet of waste receptors. Waste receptors must not be installed in concealed
spaces, and must not be installed in plenums, crawl spaces, attics, interstitial spaces above ceilings
and below floors. Ready access must be provided to waste receptors (IPC 2024, 802.4).
Sizing: a waste receptor must be sized for the maximum discharge of all indirect waste pipes served by
the receptor, and receptors must be installed to prevent splashing or flooding (IPC 2024, 802.4.1).
For the drainage load, the drainage fixture unit load of an indirect waste receptor receiving the
discharge of indirectly connected fixtures is the sum of the drainage fixture unit values of the
fixtures that discharge to the receptor, but not less than the drainage fixture unit value given for
the indirect waste receptor in Table 709.1 or 709.2 (IPC 2024, 709.4); and waste receptors such as
floor drains, floor sinks and hub drains that receive only clear-water waste from display cases,
refrigerated display cases, ice bins, coolers and freezers have a drainage fixture unit value of
one-half (IPC 2024, 709.4.1).
(25 mm) above a water-impervious floor (IPC 2024, 802.4.2).
but not greater than 42 inches (1067 mm) above the trap weir, and access must be provided to
standpipes and drains for rodding (IPC 2024, 802.4.3).
directly to a drainage system, a laundry tray waste line without a fixture trap may connect to a
standpipe for an automatic clothes washer drain. The standpipe must extend not less than 30 inches
(762 mm) above the weir of the standpipe trap and must extend above the flood level rim of the
laundry tray; the outlet of the laundry tray must not be greater than 30 inches (762 mm) horizontal
distance from the side of the standpipe (IPC 2024, 802.4.3.1).
6. Special wastes
Corrosive liquids, spent acids or other harmful chemicals that destroy or injure a drain, sewer, soil
or waste pipe, or create noxious or toxic fumes, or interfere with sewage treatment processes, must
not be discharged into the plumbing system without being thoroughly diluted, neutralized or treated by
passing through an approved dilution or neutralizing device. Such devices must be automatically
provided with a sufficient supply of diluting water or neutralizing medium so as to make the contents
noninjurious before discharge into the drainage system, and the nature of the corrosive or harmful
waste and the method of its treatment or dilution must be approved prior to installation (IPC 2024,
803.1).
A chemical drainage and vent system must be designed and installed in accordance with the code, and
chemical drainage and vent systems must be completely separated from the sanitary systems. Chemical
waste must not discharge to a sanitary drainage system until it has been treated in accordance with
Section 803.1 (IPC 2024, 803.2). The vent system for a chemical waste drainage system must be
independent of any sanitary drainage vent system, and its termination must be through the roof to the
outdoors or to an air admittance valve complying with ASSE 1049 (IPC 2024, 901.3).
Air admittance valves must not be installed in nonneutralized special waste systems as described in
Chapter 8, except where such valves comply with ASSE 1049, are constructed of materials approved in
accordance with Section 702.5, and are tested for chemical resistance in accordance with ASTM F1412
(IPC 2024, 918.8).
7. The indirect connection in the drainage load calculation
An indirect waste receptor is a drainage point of the building drain, so its load is computed as the
greater of the sum of the fixture units discharging to it and the value given for the receptor itself
in Table 709.1 or 709.2 (IPC 2024, 709.4). Where the discharge is known only as a flow rate, drainage
fixture unit values are computed on the basis that 1 gpm (0.06 L/s) of flow is equivalent to two
drainage fixture units (IPC 2024, 709.3).
Ready to test this chapter?
Practice with exam-aligned questions and timed simulations.
Start Practicing Free